Virus cluster at BDS construction site.
Posted on 5/21/20 at 10:47 am
Posted on 5/21/20 at 10:47 am
Posted on 5/21/20 at 10:54 am to BamaGradinTn
Gotta think it will delay it at least a few weeks. They were on a pretty tight schedule to begin with while working 7 days a week, weren't they?
Posted on 5/21/20 at 10:56 am to BamaGradinTn
Here is an article about it from Cecil.
LINK
I don’t think it will be a major setback
LINK
quote:
Work on the ongoing Bryant-Denny Stadium construction project at the University of Alabama was briefly suspended last weekend after an undisclosed number of workers had positive tests for COVID-19. Work resumed Monday, according to the project’s chief contractor, the Montgomery-based Caddell Construction Company.
I don’t think it will be a major setback
This post was edited on 5/21/20 at 10:57 am
Posted on 5/21/20 at 11:39 am to BamaGradinTn
SiriusXM radio was discussing about this this morning and how itmay even cause a delay to the start of college football
Posted on 5/21/20 at 12:16 pm to BamaGradinTn
They were behind before this happened. They’re in a mess.
Posted on 5/22/20 at 1:18 pm to crimson crazy
quote:
They were behind before this happened.
No they weren't. Because there was no A-Day and no scrimmages, they actually got to work through it. There are typically several hundred workers at different sites at BDS.